News

July 2017

Significant demolition is currently taking place at 182-184 High Holborn, an office refurbishment for Axa Insurance and Morgan Capital. L+C have designed the new steel frame core, additional top 3 storeys, and a new 7 storey extension to the rear.

May 2017

The renovation works at Bourlet Close are nearing completion. L+C have designed the new ground floor slab, new steel frames and foundations, side extension floors and roof, additional third storey and new roof structure, which is currently being installed.

May 2017

L+C were employed by BW to design temporary and permanent works at Edelman, 105 Victoria Street. The structural alterations included removal of three bays of the fourth floor slab, trimming steelwork around a proposed stair void, strengthening of existing slabs using carbon fibre and a new stair from third to fourth floor.

April 2017

L+C are pleased to announce that Sven Griesemann will be joining us as a Partner of the business. This is affective as of 1st April 2017. We congratulate Sven for achieving this goal, which is a result of his hard work and commitment to L+C.

April 2017

Founding Member John Lucking has retired from his full time role in the practice. However, John will continue to support the practice as a part-time Consultant.

March 2017

We performed a pre-construction visual defect survey of the Eastbound Crossrail tunnel, which runs directly below the site of our 182-184 High Holborn project. We have liaised with Crossrail throughout this project to ensure the refurbishment of the existing structure remains within Crossrail’s loading, noise and vibration criteria.

March 2017

Aldermans House project is now nearing completion after three years of hard work. L+C were appointed by ISG to design extensive temporary works including a façade retention system, demolition sequencing, underpinning, temporary propping of the existing basement, capping beam propping and a piled tower crane base.

March 2017

L+C have been appointed to produce a considerable amount of internal blockwork designs and drawings for a Canary Wharf new district. Wood Wharf is a new residential led, mixed use waterside community due for completion in 2023.

February 2017

We have been visiting the BexSimon’s workshop to inspect our designs and the progress of the artwork for Westminster Magistrates Court, which will be unveiled later in the year. Watch this space.

January 2017

L+C have been appointed to act as temporary works consultants for Barratt, who are in a process of demolishing West Ham Stadium, where new blocks of flats (including a car park basement) will be built in its place.

December 2016

L+C wish you a Merry Christmas & Happy New Year 2017!

October 2016

L+C have designed this new entrance canopy for BW as part of an office refurbishment at Bedford Park, which has now been completed.

September 2016

L+C have provided structural engineering services for the refurbishment of this pre-Victorian property in Chelsea. The project involved the complete refurbishment of the ground floor restaurant, and the refurbishment plus expansion of the first and second floors to create two new luxury two bed flats with outside terraces.

August 2016

Appointed by COMO, L+C have completed the designs for the high level joinery units and structural supports for the large display screens in the new SKY Central building.

August 2016

L+C have designed the temporary works, currently in place to restrain the existing walls to allow the staircase demolition at Great Peter Street.

July 2016

Works are nearing completion at One Mabledon Place where L+C have delivered the project using Revit in line with the procedures set out in the BIM (Building Information Modelling) execution plan, in full collaboration with ISG, SBA Architects and the rest of the design team.

May 2016

We are pleased to announce that our project at Bagley's Lane where we worked with Paul Leonard Architects has won ‘Best Individual New Home’ award at the London Regional Building Excellence Awards 2016.

March 2016

On 9th April, the final curtain will close on the Billy Elliot show at the Victoria Palace Theatre. The theatre will be extended and extensively refurbished before the start of a brand new show in late 2017. L+C are looking forward to this interesting project, where we will support the Main Contractor to achieve the ambitious construction programme.

February 2016

This is a project which we worked on with 21 Construction. The building is called the Blue Box and is for a charity called Fight for Peace. The building is constructed using a braced steel frame with concrete metal decks slabs and externally is clad with perforated metal sheeting as you can see on the photographs: http://www.arcademy.com/#!FIGHT-FOR-PEACE/c6j3/5669a24d0cf29cc3864ae7ad

January 2016

Happy New Year from all at L+C!

December 2015

We’ve designed a steel framed, split-level multi-storey car park in Crawley. The frame has been analysed using Tekla and modelled in Revit.

November 2015

L+C have been appointed to provide structural advice to the Ministry of Justice on a proposed artwork installation at Westminster Magistrates Court. We are looking forward to working closely with the Artist Blacksmiths Bex Simon and Terrence Clark to help achieve her vision for the artwork. The big unveiling is planned sometime next year.

October 2015

Work is progressing with the new roof structure at the National Gallery of Ireland in Dublin. L+C Engineers are working alongside contractors from Ireland, Holland and the UK to design, coordinate and progress the construction of several roof areas. Large steel & glass rooflights have now been installed over the Milltown Wing, with the steelwork designed by L+C to support cladding. The Merrion Entrance roof constructed from steel, timber and glass is now complete.

September 2015

L+C Facade retention design can be found in the heart of Shoreditch, an intricate steel design to retain the historic elegance of the building.

September 2015

The tower crane has been erected and basement excavation is now underway at Aldermans House.

August 2015

The basement structural works at Palace Garden Terrace are now complete. Ground floor steel work construction is underway.

July 2015

L+C have commenced the refurbishment and extension of an existing school building in Plumstead.

June 2015

L+C have commenced the refurbishment and extension of an existing restaurant and accommodation in Chelsea.